TARELCO I is now partially restored

Typhoon #KardingPH Update
As of 26 September 2022/ 1:00PM
The following transmission lines are unavailable:
NORTH LUZON
Cabanatuan-San Luis 69kV Line
Date/Time Out: 25 September 2022 / 9:11PM
Customer affected: NEECO II Area 1, NEECO II Area 2, AURELCO
Cabanatuan-Fatima 69kV Line
Date/Time Out: 25 September 2022 / 9:21PM
Customer affected: NEECO II Area 1, SAJELCO, PAMES
Cabanatuan-San Isidro 69kV Line
Date/Time Out: 25 September 2022 / 8:59PM
Customer affected: NEECO II Area 2
Cabanatuan-Bulualto 69kV Line
Date/Time Out: 25 September 2022 / 9:04PM
Customer affected: NEECO I
Concepcion-Camiling 69kV Line
Date/Time Out: 25 September 2022 / 10:16PM (partially restored)
Customer affected: TARELCO I
Four (4) 230kV lines are unavailable, particularly the Mexico-Hermosa 230kV Line 1, San Rafael-Cabanatuan 230kV Line 1, Pantabangan-Cabanatuan 230kV Line, and Mexico-Concepcion 230kV Line 2.
NGCP has mobilized its line crews and is currently conducting patrols to inspect and assess the impact of the typhoon to its operations and facilities. Simultaneous restoration activities are also being conducted on areas already accessible.
Please note that this update pertains only to the status of the transmission network. Localized disturbances may be better addressed by your distribution utility.
Specific cities and municipalities affected by the unavailable transmission facilities are determined by concerned Distribution Utilities, unless the outage affects the entire franchise area.

EMERGENCY ASSISTANCE

CONTACT INFORMATION

(045) 606 – 5374
(045) 606 – 5405
(045) 606 – 5406
info@moncadatarlac.gov.ph

VISITOR COUNTER

031094

REPUBLIC OF THE PHILIPPINES

All content is in the public domain unless otherwise stated.

ABOUT GOVPH

Learn more about the Philippine government, its structure, how government works and the people behind it.

Official Website of Municipality of Moncada