ADDITIONAL TECHNICAL ACTIVITY ON NOVEMBER 10, 2024


Please bear with us during this inconvenience and be advised to have the necessary preparations and adjustments to necessary activities ahead of the following scheduled power interruption:

PURPOSES:

1. Commissioning of Sta. Ignacia 20MVA Substation

2. Connect the previously disconnected 69kV line that supplies the power to the Sta. Ignacia Substation

* * * * * * * * * * * * * * * * * **

DATE: NOVEMBER 10, 2024 (Sunday)

TIME: 4:00 p.m. to 5:00 p.m. (1 hour)

AFFECTED AREA: TARELCO I COVERAGE AREA (ALL TOWNS)

CLICK HERE: https://www.facebook.com/share/p/1DGhT3SHV4/

Written by moncada_admin111 on .